LanguageEnglishSpanish
Request a discussion

All insights

How to read a lead time

Ask three suppliers for a lead time on the same item and you may get thirty days, sixty days, and ninety days. Often all three are accurate. They are simply measuring different things.

What a quoted figure usually excludes

A production lead time typically starts when an order is confirmed and materials are secured, and ends when goods are packed and ready. That leaves several intervals outside the number.

  • Time before confirmation: specification agreement, sampling, artwork approval
  • Raw material or component procurement, if not already held
  • Quality release, which is a defined period after production ends
  • Documentation issuance, which may follow release rather than run alongside it
  • Booking, transit, and arrival, highly variable by route and season
  • Customs and any destination-side inspection

The stages that surprise people

Two intervals cause most of the disappointment. The first is artwork and labelling approval, which can take longer than the manufacturing itself when a destination requires specific text and several parties must sign off.

The second is quality release. Product exists but cannot ship until testing completes and a responsible person signs. That period is not negotiable and should be shown separately on any schedule rather than buried inside a production figure.

Ask for a dated schedule instead of a number

A single figure invites misunderstanding. A short schedule with named stages, each with an owner and a duration, makes the assumptions visible and lets both sides see which stage is actually critical.

It also makes slippage legible. When one stage moves, everyone can see what it does to the finish date, which is far more useful than discovering a delay at the end.

Build in the decisions you control

Buyers often have more influence over the timeline than they expect, but the leverage sits early. Approving artwork quickly, confirming a specification without a second round, and having the consignee details ready all remove days.

By contrast, expediting at the end usually costs money without buying much time, because the remaining stages are the ones nobody controls.

These notes are general information for procurement professionals. They are not legal, regulatory, or medical advice, and they do not describe requirements in any specific market.

Let’s advance healthcare together.

Send us the specification, quantity, and destination market. We will tell you what is realistic before anything is quoted.